TAKT TIME CALCULATION
Before going to do the calculations, we need to have below listed data
1. Demand for all components of one department or organization for annually/monthly
2. each process cycle time
Step1: does the PQ analysis
Step2: get the total demand
Step3: get the available time ( 24 hours*365days per annuam, 24 Hours*30 days per month)
Step4: divide the total available time with total demand
Result is number of secs/mins/hours required for one product is called TAKT time